Gantt Chart Maker
Free Custom Home Template

Building a Custom Home Gantt Chart Template

A 14-month custom home build — land, design, permits, foundation, framing, dry-in, MEP, drywall, finishes, and closeout — with realistic durations and the dependencies that decide whether the schedule slips.

Open this template in the app → Download .gantt file
29 tasks 6 phases 14 months duration
May 26 Jun 26 Jul 26 Aug 26 Sep 26 Oct 26 Nov 26 Dec 26 Jan 27 Feb 27 Mar 27 Apr 27 May 27 Jun 27 Jul 27 Aug 27 Schematic design Construction documents Engineering Builder contract Submit for permit Permit review Site clearing and grading Foundation Foundation inspection Framing Roof and windows Dry-in milestone Plumbing rough-in Electrical rough-in HVAC rough-in Insulation Drywall Paint Cabinets and counters Tile and flooring Trim and millwork Plumbing and electrical t… Exterior finishes Driveway and landscaping Final inspections Certificate of occupancy Punch list Move in
Pre-built chart — click "Open this template" to load it into the app.

About this template

Building a custom home is the largest project most people ever run. The schedule is dominated by three things: how long the city takes to issue permits (1–4 months), how long the framing crew is on site (6–10 weeks), and how many decisions you can lock in before the slab is poured. This template covers a 14-month build of a single-family home on a buildable lot. Sub-divide it freely — every region runs slightly different sequences.

How a 14-month custom build breaks down

01

Design and permits

Months 1–4

Architect produces schematic design, then construction documents. Engineer signs off on structural and energy compliance. Builder bids the plans, contract gets signed, and the plans go to the city for permit. Most cities take 6–16 weeks for a single-family permit; some take longer. Use this window to also finalize finish selections so they are ready when needed.

  • Schematic design and revisions
  • Construction documents
  • Structural and energy engineering
  • Builder selection and contract
  • Submit for permit
  • Permit review and issuance
02

Site work and foundation

Months 5–6

Clear and grade the lot. Install temporary power and the construction water meter. Excavate footings. Pour foundation (slab or stem wall depending on region). Run underground plumbing. Backfill and compact. Foundation inspection before anything else goes up.

  • Site clearing and grading
  • Excavation
  • Pour footings and foundation
  • Underground plumbing
  • Foundation inspection
03

Framing and dry-in

Months 7–8

Framing crew sets the floor, walls, and roof. Sheathing goes on, roof felt and shingles, windows install, exterior doors hang. The house is "dried in" when rain no longer reaches the inside. Framing inspection signs off the structural work. This is the fastest visible progress phase — the house goes from foundation to recognizable structure in about 8 weeks.

  • Floor framing
  • Wall framing
  • Roof framing
  • Sheathing and roof
  • Windows and exterior doors
  • Framing inspection
04

Mechanical, electrical, plumbing

Months 9–10

Plumber, electrician, and HVAC contractor run pipes, wires, and ducts through the framed walls. Insulation goes in after MEP rough-in passes inspection. Drywall hang, tape, and finish takes 3–4 weeks for a typical 3,000 sq ft home.

  • Plumbing rough-in
  • Electrical rough-in
  • HVAC rough-in
  • MEP inspections
  • Insulation
  • Drywall
05

Finishes and trim

Months 11–12

Paint primer, trim install, cabinets, countertops, tile, hardwood, paint final coats, doors hang, hardware installs. Plumbing and electrical "trim out" — fixtures, faucets, light fixtures, switches. Appliances install. Exterior is also progressing — siding, paint, driveway, landscaping.

  • Paint primer
  • Trim and millwork
  • Cabinets and countertops
  • Tile and flooring
  • Plumbing fixtures
  • Electrical fixtures
  • Appliances
  • Exterior finishes
  • Driveway and walkways
06

Closeout and move-in

Months 13–14

Final inspections, certificate of occupancy, final walkthrough with builder, punch list, landscaping, and move-in. Most builders offer a 1-year warranty walkthrough at the end of year 1.

  • Final inspections
  • Certificate of occupancy
  • Punch list
  • Landscaping
  • Final walkthrough
  • Move in

Tips from finished custom builds

Frequently asked questions

How long does it take to build a custom home?

10–18 months for most builds, depending on size, complexity, and permitting time. This template targets the 14-month middle case.

What is the most-missed risk?

Permit review time. Some jurisdictions issue in 6 weeks; others take 16. Ask the builder for the local average before you sign the contract.

When should I select finishes?

During design — before the slab is poured. Late selections become change orders and slow the schedule.

Related templates

Start planning in 30 seconds

Open the custom home template and shape it to your build — lot, design, builder, finishes. The app runs entirely in your browser and is free forever.

Open this template →