Kitchen Remodel Gantt Chart Template

A 10-week kitchen remodel timeline — design, cabinets, demo, rough-in, drywall, finishes, and appliance install — with realistic lead times for cabinets and countertops.

Open this template in the app → Download .gantt file
21 tasks 5 phases 10 weeks duration
May 26 Jun 26 Jul 26 Aug 26 Lock design Order cabinets Order appliances Order tile and flooring Demolition Framing changes Plumbing rough-in Electrical rough-in Rough inspection Drywall Paint Flooring install Cabinet install Countertop template Backsplash tile Countertop install Appliance install Plumbing fixtures Final inspection Punch list
Pre-built chart — click "Open this template" to load it into the app.

About this template

Kitchens are the most logistically dense room to renovate. Cabinets have a 4–8 week lead time, countertops install 1–2 weeks after cabinets are set, and the plumber and electrician have to fit between the framer and the drywaller without anyone tripping over each other. This 10-week template assumes the design is mostly settled when day 1 starts and the cabinets were ordered at least 6 weeks earlier.

How a 10-week kitchen remodel breaks down

01

Design lock and ordering

Weeks 1–2

Confirm the layout, finish selections, and appliance package. Order cabinets immediately — the rest of the schedule depends on when they show up. Order tile, flooring, lighting, and the appliances within the same week so deliveries land before you need them, not after.

  • Finalize layout
  • Order cabinets (4–8 week lead time)
  • Select and order tile, flooring, lighting
  • Order appliances
02

Demo and rough-in

Weeks 3–5

Demo is 2–3 days. Then the trades come in sequence: framing changes (for new openings or moved walls), plumbing rough-in (relocating supply and waste lines), electrical rough-in (new circuits for the range, outlets at island, under-cabinet lighting), and HVAC if any duct work moves. All have to pass rough inspection before drywall goes up.

  • Demolition (2–3 days)
  • Framing changes
  • Plumbing rough-in
  • Electrical rough-in
  • Rough inspection
03

Drywall, paint, and floor

Weeks 6–7

Drywall hang and finish takes 5–7 days. Prime and paint walls and ceilings before cabinets go in — you can never paint behind a cabinet once it is installed. Floor tile or LVP usually installs before cabinets so the cabinet toe-kick sits on a finished floor.

  • Drywall hang and tape
  • Joint compound and sanding
  • Prime and paint
  • Floor install
04

Cabinets and countertops

Weeks 8–9

Cabinet install takes 2–4 days for an average kitchen. The day after cabinets are set, the countertop fabricator comes to template the stone. Template-to-install is 7–10 business days for quartz and granite. Build that gap into the schedule — most DIY plans assume same-week install and end up living off a card table for ten days.

  • Cabinet install
  • Countertop template
  • Backsplash (after countertop install)
  • Countertop install
05

Appliances, plumbing, and final

Week 10

Appliances, plumbing fixtures (faucet, sink, disposal, dishwasher), and lighting all install in the final week. Final inspection follows, then the punch-list walkthrough — caulk lines, hardware adjustment, the cabinet door that needs a hinge tweak.

  • Appliance install
  • Plumbing fixtures and dishwasher
  • Lighting install
  • Final inspection
  • Punch list

Tips from finished kitchen remodels

Frequently asked questions

How long does a kitchen remodel take?

8–12 weeks for a typical remodel with no structural changes; 12–16 weeks if walls are moving or you add a peninsula or island.

When should I order cabinets?

Order cabinets 6–10 weeks before demo day. Lead times have stayed long since 2022 — order the moment your design is locked.

Can I live in the house during the remodel?

Yes, but set up a temporary kitchen with the microwave, fridge, and a folding table. The dust during demo and drywall is unavoidable; seal off the kitchen with plastic sheeting.